At HUSUM WIND 2025, Caeli Wind will demonstrate how its digital marketplace accelerates wind project ...
December 2015
On 23 December 2015 Leitwind completed the installation and commissioning of two LTW86 1.5MW wind turbines for the 3MW Moszczenica wind project in Poland. In April 2015 Leitwind received the order for these two turbines from EIG Ekologiczna Elektrownia Sp. Z o. o. The project has been developed by the project developer Siłownie Wiatrowe SA (SWSA). The turbines are installed with a new tower configuration with a hub height of 100 metres. Leitwind will also be responsible for servicing the wind turbines for the next 15 years.
At HUSUM WIND 2025, Caeli Wind will demonstrate how its digital marketplace accelerates wind project ...
Parliamentary State Secretary Stefan Rouenhoff will open the wind trade fair on 16 September / ...
Honoured for driving digital innovation in wind energy, Caeli Wind joins Energize Capital’s list of ...